(Solved): Production wokers for Stuart Manufacturing Company provided 380 hours of labor in January and 560 ho ...



Production wokers for Stuart Manufacturing Company provided 380 hours of labor in January and 560 hours in February. Stuart expects to use 4000 hours of labor during the year. The rental fee for the manufacturing faciillity is $10,000 per month. 

Based on this information, how much of the rental cost should be allocated to the products made in January and to those made in February? (Do not round intermediate calculations) 

MonthAllocated Cost 
January 
February  